Re: Ford Site Redevelopment

Reclamation continues, should have all of the existing asphalt/concrete surfaces removed and stockpiled by the end of next week. Onsite crushing of those materials should happen soon after that, probably will take 8-10 days to process. No word on how close the city is to approving the modified utili...
by Cat349F
April 7th, 2020, 8:54 pm
Forum: Transportation
Topic: Green Line Extension - Southwest LRT
Replies: 5265
Views: 1247425

Re: Southwest LRT (Green Line Extension)

There will be an acceleration of the 94 re-surfacing from 280 to Nicollet due to the shelter order. That is the only project I have heard being pushed up.
by Cat349F
April 1st, 2020, 6:45 am
Forum: Minneapolis - Downtown
Topic: Foundry Mixed-Use Development - 115-125 1st St N, 128 2nd St N, 128 1st Av N
Replies: 128
Views: 289063

Re: Foundry Mixed-Use Development - 115-125 1st St N, 128 2nd St N, 128 1st Av N

The building is being moved out onto 2nd while we do the foundation work.
by Cat349F
March 24th, 2020, 4:05 pm
Forum: Minneapolis - North, Northeast, and Southeast / University of Minnesota
Topic: Art and Architecture Building Development - 3338 University Ave SE - 14 Stories / 155'
Replies: 120
Views: 200903

Re: Art and Architecture Building Development - 3338 University Ave SE - 14 Stories / 155'

No that is a separate project for an extended stay hotel Home2.
Thank you.

The Home2 developer is allowing us to finish the demolition and stabilize the site. They will not begin building until things settle down.
by Cat349F
March 23rd, 2020, 8:53 am
Forum: Transportation
Topic: Work from home and road congestion
Replies: 28
Views: 8333

Re: Work from home and road congestion

For those living in apartments or still working in an building with elevators, how are you handling that aspect? Is the elevator disinfected regularly? How do you handle crowded stairwells? I moved my oldest daughter home from college yesterday. Two trips required use of the elevator. (heavy items) ...
by Cat349F
March 19th, 2020, 7:46 pm
Forum: Saint Paul
Topic: Highland Bridge: Ford Site Redevelopment
Replies: 199
Views: 163824

Re: Ford Site Redevelopment

We have begun work. Reclamation of asphalt and concrete surfaces will be stockpiled at the south end of the former paint building footprint. Once crushing starts, it will be stockpiled on-site, at the south end of the paint parking lot. The deer are annoyed. The coyotes are skittish. The ducks are i...
by Cat349F
March 19th, 2020, 7:29 pm
Forum: Transportation
Topic: Work from home and road congestion
Replies: 28
Views: 8333

Re: Work from home and road congestion

Interesting about the U.K. I doubt the same holds true here, I am of the opinion most people don’t adjust/program their thermostat to conserve while at work.
by Cat349F
March 15th, 2020, 8:11 pm
Forum: Minneapolis - Downtown
Topic: Archive Apartments - 110 1st Street N
Replies: 161
Views: 54111

Re: Archive Apartments (Not West Elm Hotel & Condos) - 102-120 1st Street N

Ground retention anchors have been removed from the sub-levels. The post-tension decks have all reached their 90 day cures, and the connecting pour strips all passed and are cured.
Our remaining work is to remove and replace the sidewalk when the project nears completion.
by Cat349F
March 15th, 2020, 8:02 pm
Forum: Minneapolis - Downtown
Topic: The Gatsby - 1400 Park Avenue
Replies: 155
Views: 90705

Re: 1400 Park Avenue

The last of the foundation work in the NE corner is complete. We should see considerable progress in the coming weeks.
by Cat349F
March 11th, 2020, 8:37 pm
Forum: Minneapolis - Downtown
Topic: 240 Hennepin Ave - 21 stories - 256'
Replies: 132
Views: 121076

Re: Harlem Irving and CA Ventures - 250 Hennepin Ave - 21 stories - 256'

It is coated cable for a post-tensioned concrete deck.
by Cat349F
March 7th, 2020, 9:30 pm
Forum: Saint Paul
Topic: Highland Bridge: Ford Site Redevelopment
Replies: 199
Views: 163824

Re: Ford Site Redevelopment

I do have couple of small items to share. Ryan is placing their job site office trailer on the east side, directly south of Lunds. Excellent visibility of the site there. Access will be next to the employee parking lot behind their store. They open at 6:00, city has a noise ordinance thru 7:00. No e...
by Cat349F
March 7th, 2020, 9:04 pm
Forum: Saint Paul
Topic: Highland Bridge: Ford Site Redevelopment
Replies: 199
Views: 163824

Re: Ford Site Redevelopment

We have begun to mobilize equipment back onto the site, but no word yet on when work will begin.
by Cat349F
February 21st, 2020, 9:48 pm
Forum: Saint Paul
Topic: Highland Bridge: Ford Site Redevelopment
Replies: 199
Views: 163824

Re: Ford Site Redevelopment

This is a very concerning aspect of the Ford Site that I had no idea existed until recently- a huge potentially toxic waste dump on the river floodplain: https://fmr.org/river-corridor-and-land-use-updates/area-c-overlooked-ford-site It's separate from the area being redeveloped, so it shouldn't ha...
by Cat349F
February 20th, 2020, 7:46 pm
Forum: Saint Paul
Topic: Highland Bridge: Ford Site Redevelopment
Replies: 199
Views: 163824

Re: Ford Site Redevelopment

Pending plan and permits approval, earthwork to start March 16th.
Equipment staging could begin next week.
by Cat349F
February 16th, 2020, 3:34 am
Forum: Minneapolis - Downtown
Topic: The Gatsby - 1400 Park Avenue
Replies: 155
Views: 90705

Re: 1400 Park Avenue

Stormwater retention tanks have been installed in the NE corner. The rest of the foundation in that corner (which only goes down one story, not two) can now be installed.
Demolition of the church on the west side rumors are swirling once again.
by Cat349F
February 16th, 2020, 3:26 am
Forum: Minneapolis - Downtown
Topic: Foundry Mixed-Use Development - 115-125 1st St N, 128 2nd St N, 128 1st Av N
Replies: 128
Views: 289063

Re: Foundry Mixed-Use Development - 115-125 1st St N, 128 2nd St N, 128 1st Av N

According to someone who works for the company moving it, (but not on this project specifically) the building is staying onsite?
by Cat349F
February 7th, 2020, 4:54 pm
Forum: Minneapolis - Downtown
Topic: 240 Hennepin Ave - 21 stories - 256'
Replies: 132
Views: 121076

Re: Harlem Irving and CA Ventures - 250 Hennepin Ave - 21 stories - 256'

It looks like pre-cast concrete decking, but it’s too small.
by Cat349F
February 6th, 2020, 6:51 pm
Forum: Minneapolis - Downtown
Topic: 240 Hennepin Ave - 21 stories - 256'
Replies: 132
Views: 121076

Re: Harlem Irving and CA Ventures - 250 Hennepin Ave - 21 stories - 256'

Yes. Aaaaand they’re off!

They will pass Gateway by July.
by Cat349F
January 29th, 2020, 5:55 pm
Forum: Saint Paul
Topic: Saint Paul - General Topics
Replies: 694
Views: 385902

Re: Saint Paul - General Topics

Highland 9 hole proposal to reuse the land for soccer fields, skate park, and pickle ball. Thank goodness they’re going over there. The 18 hole side is a nightmare. The water towers on the west side leak (a lot) so bad that they didn’t have pipe in a water supply, they just pump out of the ponds on...