Kraus-Anderson, HQ Apartments, Finnegans "Brewtel" - 9th St S/5th Ave S

Downtown - North Loop - Mill District - Elliot Park - Loring Park
bapster2006
Foshay Tower
Posts: 907
Joined: November 17th, 2012, 6:53 pm

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby bapster2006 » March 10th, 2016, 9:12 am

The planning commission looks at this project on Monday

Qhaberl
Foshay Tower
Posts: 856
Joined: February 25th, 2016, 9:51 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby Qhaberl » March 10th, 2016, 9:31 am

Hope it goes through.

twinkess
Target Field
Posts: 529
Joined: November 26th, 2012, 10:46 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby twinkess » March 14th, 2016, 12:02 pm

CPED Staff Report http://minneapolismn.gov/www/groups/pub ... 175044.pdf

I'll likely go to this meeting out of curiosity.

User avatar
mister.shoes
Wells Fargo Center
Posts: 1297
Joined: November 26th, 2012, 10:22 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby mister.shoes » March 14th, 2016, 12:31 pm

Pretty sure I've posted something to this effect on every page of this thread, but I'm just all sorts of irrationally excited about this project. And I'm still completely pissed? baffled? annoyed? that Opus can't follow K/A's lead and stick all their effing parking underground. Not to mention pull off four active block faces and honest-to-goodness mixed use. Le sigh.
The problem with being an introvert online is that no one knows you're just hanging out and listening.

User avatar
Nathan
Capella Tower
Posts: 3649
Joined: June 1st, 2012, 10:42 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby Nathan » March 14th, 2016, 1:01 pm

Can we offer them a block swap? For real!?

mullen
Foshay Tower
Posts: 939
Joined: June 4th, 2012, 7:02 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby mullen » March 14th, 2016, 5:01 pm

this is the best development happening downtown.

Wedgeguy
Capella Tower
Posts: 3343
Joined: June 1st, 2012, 6:59 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby Wedgeguy » March 14th, 2016, 9:21 pm

I'm looking forward to seeing the construction fences going up around this block. Curious to see if they start working on the 8th street side and work their way towards 8th. This would allow for the Portland to get as much work done before they have to squeeze the traffic lanes down. Hope they have most of the Portland 8th street side done so they will be able to get the construction barriers of the north side of 8th before the south sides are put in place or the restricted lane period is shorter.

Qhaberl
Foshay Tower
Posts: 856
Joined: February 25th, 2016, 9:51 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby Qhaberl » March 15th, 2016, 6:20 am

this is the best development happening downtown.
I totally agree. I was looking at the prior ideas proposed by Kraus Anderson. They really did a nice job making full use of the block. Hopefully we get to see more developments like this. Way to go KA!!!

User avatar
seamonster
Nicollet Mall
Posts: 150
Joined: May 14th, 2015, 1:12 pm

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby seamonster » March 15th, 2016, 6:37 am

What I find most interesting about this development is how KA threw in everything after offering zero initially - isn't that how it played out? It reminds me of encouraging toddlers to share:

"Kraus, it would be nice for you to give Minneapolis a cookie. You have plenty and Minneapolis has none."

"FINE! Take my cookies! Take all of them! Have my juicebox, too - you want a brewery? THERE. And a HOTEL? TAKE IT! I'll even give you a WOONERF! AND HOUSING! OVER SIX STORIES! NOW ARE YOU HAPPY?"

Yes. I'm happy.
Totally forgot to include the underground parking in my original post! I absolutely agree that this is best development happening downtown.

Wedgeguy
Capella Tower
Posts: 3343
Joined: June 1st, 2012, 6:59 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby Wedgeguy » March 18th, 2016, 6:58 pm

Was reading F&C today at the library. Sound like they plan to start work in April. They will be doing it in stages with the parking done first, the office tower and hotel/brewery done so that both are open by the Superbowl. the apartments would come last, but had hoped that the whole project would be done in by 2019.
Finnegans will be the owner of both the brewery, event center, and the hotel. So we will see how that works out for them.

twinkess
Target Field
Posts: 529
Joined: November 26th, 2012, 10:46 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby twinkess » March 21st, 2016, 4:53 pm

Equipment on site! Anyone know what this is? Pile driver?

Image

go4guy
Foshay Tower
Posts: 917
Joined: June 4th, 2012, 8:54 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby go4guy » March 21st, 2016, 5:49 pm

I have no idea, but I would assume that is for taking samples? I wouldn't think a pile driver would go on site until the have cleared the site of all asphalt and concrete. But I am not expert.

twinkess
Target Field
Posts: 529
Joined: November 26th, 2012, 10:46 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby twinkess » March 23rd, 2016, 11:37 am


TroyGBiv
US Bank Plaza
Posts: 659
Joined: July 6th, 2012, 10:33 pm

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby TroyGBiv » March 23rd, 2016, 11:57 am

This is a great view!!!! I now realize how many open blocks there are available for development in that area...

grant1simons2
IDS Center
Posts: 4347
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby grant1simons2 » March 23rd, 2016, 12:08 pm

It looks like there may already be some interior demolition based on the dumpster and storage trailers.

amiller92
Wells Fargo Center
Posts: 1988
Joined: October 31st, 2014, 12:50 pm

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby amiller92 » March 23rd, 2016, 12:15 pm

Equipment on site! Anyone know what this is? Pile driver?
It's got a sign on the side that says, "Pileco" so I assume so.

twinkess
Target Field
Posts: 529
Joined: November 26th, 2012, 10:46 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby twinkess » March 23rd, 2016, 12:37 pm

Equipment on site! Anyone know what this is? Pile driver?
It's got a sign on the side that says, "Pileco" so I assume so.
:lol: oops

User avatar
Nathan
Capella Tower
Posts: 3649
Joined: June 1st, 2012, 10:42 am

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby Nathan » March 23rd, 2016, 12:41 pm

So I just want to clarify, The office building, Brewtel and Finnegans brewpub are phase one, and then the apartments are phase two? You'd think with the news that demand for apartments downtown isn't slowing they'd just go for it, or do you think they just want that space for staging materials and then they'll do the apartments right after?

aeisenberg
Landmark Center
Posts: 263
Joined: June 12th, 2012, 7:45 pm

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby aeisenberg » March 23rd, 2016, 3:08 pm

Equipment on site! Anyone know what this is? Pile driver?
It's got a sign on the side that says, "Pileco" so I assume so.
plus one.
Aaron Eisenberg / Realtor, Keller Williams Integrity
612.568.5828 / [email protected] / 1350 Lagoon Ave #900
http://www.agentaaron.com

grant1simons2
IDS Center
Posts: 4347
Joined: February 8th, 2014, 11:33 pm
Location: Marcy-Holmes

Re: New Kraus-Anderson HQ (9th St. S/5th Ave. S)

Postby grant1simons2 » March 23rd, 2016, 5:17 pm

"So long old HQ"

http://www.krausanderson.com/blog/2016/03/

Also saw on their site that their last day at the downtown HQ is tomorrow.