The Gatsby - 1400 Park Avenue
Re: 1400 Park Avenue
"1. All site improvements shall be completed by August 29, 2018, unless extended by the
Zoning Administrator, or the permit may be revoked for non-compliance."
from the packet... nothing like waiting till the ultimate last second
Zoning Administrator, or the permit may be revoked for non-compliance."
from the packet... nothing like waiting till the ultimate last second
Re: 1400 Park Avenue
They can be extended administratively, without an additional public process. That's how the City Club Apartments at 10th and Marquette abruptly rose from the dead about 2.5 years after it was approved.
Joey Senkyr
[email protected]
[email protected]
Re: 1400 Park Avenue
Is there a way for us common folk to know if something has been administratively extended? That makes sense about city club Apartments, I’ve been racking my head about that.
Sent from my iPhone using Tapatalk
Sent from my iPhone using Tapatalk
Re: 1400 Park Avenue
I think I saw some equipment on site? Something may be finally starting here.
Re: 1400 Park Avenue
Yesterday morning there was Xfinity equipment on site, so I assumed they weren't beginning to build anything (but had the same thought as I was approaching before I could see the markings).
Re: 1400 Park Avenue
When do the planning Commission approvals expire?
Sent from my iPhone using Tapatalk
Sent from my iPhone using Tapatalk
Re: 1400 Park Avenue
This is right out my window and nothing has happened.
Re: 1400 Park Avenue
Appears to still be happening. Utility work soon:
https://finance-commerce.com/2018/12/wh ... k-project/
https://finance-commerce.com/2018/12/wh ... k-project/
Re: 1400 Park Avenue
That's great. This is a horribly ugly block right now.
Re: 1400 Park Avenue
There is a construction trailer and barriers up on this project.
Still need to do demo work on the existing ex-MN AIDS Project building
Still need to do demo work on the existing ex-MN AIDS Project building
- seamonster
- Nicollet Mall
- Posts: 150
- Joined: May 14th, 2015, 1:12 pm
Re: 1400 Park Avenue
Demolition has begun.
Re: 1400 Park Avenue
Has anything happened with the old church adjacent to this project (discussed upthread)?
Re: 1400 Park Avenue
From what I saw, the plans for this went before the planning commission more than two years ago, doesn’t that mean that the plans must be approved again?
Sent from my iPhone using Tapatalk
Sent from my iPhone using Tapatalk
Re: 1400 Park Avenue
Is this still the plan?
Re: 1400 Park Avenue
That’s what I was wondering. That’s the last thing I saw go before the planning commission. Like I said, I believe that was over two years ago.Is this still the plan?
Sent from my iPhone using Tapatalk
Re: 1400 Park Avenue
No. There's a different rendering in the article just a few posts up.Is this still the plan?
Re: 1400 Park Avenue
That’s really strange. Why didn’t they have to go back to the planning commission with the aesthetic changes?
Rant:
It really bothers me that developers don’t have to stick to the aesthetic proposals that go before the planning commission. In my opinion, if you tell the city that this is what the building will look like, that’s exactly what the building should look like when it’s completed. I really hope that’s an area Minneapolis works on. Holding developers accountable to the aesthetic design they submit to the planning commission.
Sent from my iPhone using Tapatalk
Rant:
It really bothers me that developers don’t have to stick to the aesthetic proposals that go before the planning commission. In my opinion, if you tell the city that this is what the building will look like, that’s exactly what the building should look like when it’s completed. I really hope that’s an area Minneapolis works on. Holding developers accountable to the aesthetic design they submit to the planning commission.
Sent from my iPhone using Tapatalk
Re: 1400 Park Avenue
Yes, but that was the original rendering from 2015 or so. The one I posted was the their updated plan in 2016.No. There's a different rendering in the article just a few posts up.Is this still the plan?
-
- Foshay Tower
- Posts: 911
- Joined: November 17th, 2012, 6:53 pm
Re: 1400 Park Avenue
The planning commission granted this project approval in April 2016. Then in August 2016 they went back to the planning commission for a revision. The plans are here:
http://www.ci.minneapolis.mn.us/www/gro ... 185554.pdf
Last year they were granted an extension until August 2019.
http://www.ci.minneapolis.mn.us/www/gro ... 185554.pdf
Last year they were granted an extension until August 2019.