Not that I can find, even the GC calls it 1400 Park. All blueprints label the project 1400 Park. I will ask.Anyone want to do some sleuthing to find out if this project has a name? Check demo/building permits, etc...
Pre-cast install is 15-20% complete. Exterior walls of the basement are complete on the south and west sides, east side is 50% complete, north wall started last Friday.
The NE corner, at Grant and Park, only has one sub level. Due to the access ramp for pre-cast deliveries, that corner will be built last.
At least 6 weeks until a tower crane gets erected on the south side.