Alia Tower - 200 Central - 483' / 40 Stories
-
- Foshay Tower
- Posts: 913
- Joined: November 17th, 2012, 6:53 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Nope, because NEBL would have to appeal to them for that fourth complaint and they haven't even applied to the regular appeals court for that one.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Bapster thank you for all your knowledge and insight on this project. It's been very helpful.
-
- Capella Tower
- Posts: 2869
- Joined: June 1st, 2012, 9:19 am
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Yes, thanks bapster! It's much appreciated!!
-
- IDS Center
- Posts: 4615
- Joined: December 4th, 2012, 11:41 am
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
ROFL! IANAL has been an acronym since back before the internet was a household name, so I didn't even consider other interpretations...I laughed at this way too much this morning, imagining an unfortunate autocorrect and a new Apple product iANAL.But IANAL.
Alas, I learned it's just an acronym - "I am not a lawyer."
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
I think it also stopped being an acronym before the internet was a household name.
(IALTO)
(IALTO)
-
- IDS Center
- Posts: 4615
- Joined: December 4th, 2012, 11:41 am
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Oof.I think it also stopped being an acronym before the internet was a household name.
I think I first encountered it on FidoNet, when I was readi*%&^#*$@#!%NO CARRIER
-
- Foshay Tower
- Posts: 913
- Joined: November 17th, 2012, 6:53 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
You are welcome!
Oral arguments are scheduled at the Appeals court for October 26. Two more months to wait and I am very curious what they will be talking about since NEBL has been shot down on everything.
Oral arguments are scheduled at the Appeals court for October 26. Two more months to wait and I am very curious what they will be talking about since NEBL has been shot down on everything.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Wait, what's going to the appeals court now? I thought it had already been through there and to the Supreme Court?
Joey Senkyr
[email protected]
[email protected]
-
- Foshay Tower
- Posts: 913
- Joined: November 17th, 2012, 6:53 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Yeah, it gets weird real quick because of all the different complaints that are going on. The Supreme Court turned down NEBL on the complaint that the building would be bad for the environment. The bond was sent back to the district court who quickly dismissed all the complaints and closed the case. The height issue was dismissed by the district court and NEBL has not appealed that decision. Of course, NEBL can end the appeal at anytime when they run out of cash.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
So what's scheduled at the appeals court then, if the height issue didn't get appealed and the environmental issue is closed?
Joey Senkyr
[email protected]
[email protected]
-
- Foshay Tower
- Posts: 913
- Joined: November 17th, 2012, 6:53 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
The District Court is finally going to make a judgment on that bond amount. The final amount will be somewhere between $100,000 and $5.9 million.
If NEBL can't pay, then tye remnants of what's left will crumble apart.
If NEBL can't pay, then tye remnants of what's left will crumble apart.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Fingers crossed.
Joey Senkyr
[email protected]
[email protected]
-
- Foshay Tower
- Posts: 913
- Joined: November 17th, 2012, 6:53 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
On October 6 there is a motion hearing to settle all of this in District Court.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
To settle what? I thought there was nothing left to settle.
Sent from my iPhone using Tapatalk
Sent from my iPhone using Tapatalk
-
- Foshay Tower
- Posts: 913
- Joined: November 17th, 2012, 6:53 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
The only thing left in the District Court is the new bond amount for the Stay of demolition.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
The bond amount was announced today as being roughly $4.5 million. Plaintiffs have one week to raise it.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Lol. Good luck with that!The bond amount was announced today as being roughly $4.5 million. Plaintiffs have one week to raise it.
-
- Foshay Tower
- Posts: 913
- Joined: November 17th, 2012, 6:53 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
Update cheat sheet:
Counts 1, 5: Filed 11/21/16, Dismissed by district court 7/24/17, Appeal filed 9/22/17
Counts 2, 3, 4: (MERA claim) Filed 11/21/16, Dismissed by district court 3/30/17 - Appeal filed 5/25/17, Oral argument at Appeals court 10/26/17
Bond: Bond and Stay of demolition granted 5/25/17 for $100,000 - Appeals court remanded back to District Court 6/27/27. Supreme Court petition filed 6/29/17, rejected 8/22/17. District Court signs Order 9/22/17 for NEBL to post a bond of $2.89 million for the City and $1.68 million for Alatus by 4pm on Friday.
So if the bond is not paid, demolition can proceed and then they will finish the arguments in the Appeals court about the MERA (environmental) and height arguments.
Counts 1, 5: Filed 11/21/16, Dismissed by district court 7/24/17, Appeal filed 9/22/17
Counts 2, 3, 4: (MERA claim) Filed 11/21/16, Dismissed by district court 3/30/17 - Appeal filed 5/25/17, Oral argument at Appeals court 10/26/17
Bond: Bond and Stay of demolition granted 5/25/17 for $100,000 - Appeals court remanded back to District Court 6/27/27. Supreme Court petition filed 6/29/17, rejected 8/22/17. District Court signs Order 9/22/17 for NEBL to post a bond of $2.89 million for the City and $1.68 million for Alatus by 4pm on Friday.
So if the bond is not paid, demolition can proceed and then they will finish the arguments in the Appeals court about the MERA (environmental) and height arguments.
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
By the time this is all done...I am pretty doubtful the tower will still move forward. We shall see.
-
- Foshay Tower
- Posts: 980
- Joined: February 20th, 2015, 12:38 pm
Re: 200 Central - Alatus Tower (Washburn-McReavy Site) 483' / 40 Stories
On the contrary, I don't think Alatus would have wasted this much time only to give up. If there was demand for 40 stories of condos before this neighborhood bull, there's still demand now.
Who is online
Users browsing this forum: No registered users and 5 guests